Utilities and grid operators are focused on making sure the electric grid can always meet demand. This is called resource adequacy. Ensuring resource adequacy involves short- and long-term planning, coordination, and maintenance.

Here’s a breakdown of key factors and challenges behind resource adequacy.

 

Enough Capacity

On the surface, this is a simple equation of whether there is more generating capacity in operation than the peak usage on high demand days.

U.S. July 2025 peak demand over total nameplate capacity, or 759,180 MW over 1,326,426 MW

U.S. peak demand, July 2025

Total U.S. nameplate capacity

However, the nameplate capacity does not equal output, and operators are looking at how to better measure total capacity based on how often it gets dispatched. Worth noting that of the total U.S. nameplate capacity, only 870,600 MW is firm capacity.

 

Sufficient Transmission

As of early 2025, 468,582 MW of new generating capacity was under development, including 143,247 MW that have been permitted or are under construction. Since 2000, less than 20% of generation projects have been completed, in part due to increasing wait times to interconnect to the grid.

Building more capacity is one step, delivering the generated power to whoever will use it via transmission lines is another.

As of January 2026, 41,000
miles of transmission lines
were in some stage of
development across the U.S.
(through 2035)
Total miles of transmission lines under development in the U.S. as of January 2026

Of the 863 transmission
projects in the pipeline,
390 are facing delays.

Total number of U.S. transmission projects in the pipeline as of January 2026.

Projects totaling more than
3,616 miles of transmission
lines were added between
2023 – October 2025.

Miles of transmission lines added to the U.S. grid between 2023 - October 2025.

Accurate Forecasting

With more variable generating capacity sources on the grid, operators need to predict not only how much load will be needed in the future, but when it will be needed. In many regions of the U.S., electricity demand tends to peak in the later afternoon during July and August.

 

Projected Peak Load Growth, 2026-2032

NERC's Long-Term Reliability Assessment projects peak demand to grow more than 170 gigawatts through 2032. However, this demand is not spread evenly across the U.S.

 

Map of peak load growth by region.
RegionPeak Load Growth
ERCOT53.9 GW
PJM41.6 GW
West28.1 GW
Southeast19.7 GW
MISO14.9 GW
SPP9.5 GW
New England & New York2.8 GW

Download the full graphic