Across the United States, there are over 950 data centers in operation, including 196 inside 89 unique public power service areas.
By the Numbers
- 1 in 5 data centers in operation are in public power areas
- 16 public power utilities have 4 or more operating within their service territory
- 13 MW median capacity* of data centers in operation in public power areas (compared to 8 MW for data centers operating outside public power areas)
- 39 of the 250 data centers under construction (16%) are in public power areas
- 133 of 668 projects either permitted or proposed are in public power service territory (20%)
- 200 MW median capacity* of permitted or proposed data centers in public power areas (compared to 300MW for data centers outside public power territory)
- 6 data centers in public power areas have operational capacities of 100 MW or more, and 61 data centers under construction, permitted, or proposed in public power areas expect to have operational capacities of 100 MW or more
- 18% of data centers proposed in public power areas have planned capacities of 500MW or greater, compared to 45% of proposed data centers outside public power service territories

- Silicon Valley Power serves the highest number of operational data centers in public power, with 23
- Texas has the most data centers under construction, including 7 in public power areas
- Georgia has the most data centers permitted in public power communities, with 9, or 45% of permitted projects in the state
- The data center reporting* both the highest operational capacity (590 MW) and proposed capacity (2.2 GW) in a public power service area is an Amazon facility in New Carlisle, IN
Source: “U.S. Data Center Map & Database”, October 2026, Compute Atlas. www.compute-atlas.com
*Note: Less than half of projects included in the data set had either an operational or proposed capacity figure.