The Southwest Power Pool Board of Directors on Nov. 17 approved the 2026 Integrated Transmission Plan (ITP), the highest-value transmission portfolio in the organization's history, "projected to deliver $2.27 to $6.38 in benefits for every dollar invested while supporting new generation, economic growth and a more reliable, resilient grid," it said.

At its Nov. 17 meeting, the board authorized SPP to issue notification to construct (NTC) letters for select projects in the approved portfolio. 

The portfolio includes new and upgraded transmission lines designed to move more electricity across the region. SPP evaluated more than 14,000 potential projects and worked with hundreds of stakeholders over two years to develop a portfolio that will make the SPP system more reliable, lower costs and increase operational capabilities.

"The 2026 ITP addresses grid reliability, enables economic growth and supports energy affordability," said Casey Cathey, SPP vice president of engineering. "Independent sources validate the significant load growth our region is facing, and this plan positions SPP to meet those needs while increasing operational capabilities."

SPP said the approved NTC portfolio will drive significant regional benefits:

  • $76 billion to $215 billion in modeled adjusted production cost benefits over 40 years, reducing the cost of serving electricity demand across the region. Benefits are expressed in net present value across the two planning scenarios. The total cost of projects receiving an NTC is $23.7 billion. Customer impacts will vary based on cost allocation and other factors.
  • About 35 gigawatts of additional transfer capability to move more electricity across the region. The portfolio could also add about 40 gigawatts of capacity to connect new electricity customers and generation.
  • Approximately one gigawatt of potential reduction in transmission losses, alongside reliability and operational benefits not fully captured in adjusted production cost.

The 2026 ITP study projects peak electricity demand could rise from about 58 gigawatts in 2026 to about 72 gigawatts by 2030 and 96 to 110 gigawatts by 2035. 

Congestion is already becoming more widespread, with the number of distinct peak transmission constraints rising from 115 in 2016 to 302 in 2025.

The portfolio includes a 765-kV transmission backbone that will create an “expressway” for ultra-high-voltage transmission. 765-kV lines provide high-capacity transfer capability and can serve rapid load growth over longer distances with lower losses, it noted.

SPP evaluated higher-capacity transmission to address the scale of needs identified in the portfolio. In the buildout evaluated, the 765-kV alternative requires nine lines, compared with 41 lines required for a 345-kV alternative. The 345-kV alternative costs approximately 1.9 times as much as the 765-kV alternative.

"The 2026 ITP reinforces SPP's commitment to a reliable, affordable and resilient electric grid," Cathey said. "This portfolio provides the transmission backbone needed to support new generation, accommodate accelerating demand and deliver long-term value to the region.”