Powering Strong Communities
Generation

PJM Says Delaware Power Plant Can Retire Two Years Ahead of Schedule

Like What You Are Reading?

Please take a few minutes to let us know what type of industry news and information is most meaningful to you, what topics you’re interested in, and how you prefer to access this information.

The PJM Interconnection in December announced that Indian River Unit 4, a coal-fired generator in Delaware owned by NRG, can retire nearly two years ahead of its currently scheduled deactivation without adverse impacts to reliability.  

Delmarva Power, the transmission owner in this region, has completed the needed transmission additions that will enable Indian River 4, a 411 MW electrical generator located in southern Delaware, to retire 22 months before its scheduled deactivation date, saving wholesale electricity customers approximately $93 million, PJM said.

PJM, in coordination with Delmarva, has made the determination that Indian River 4 is no longer needed for the reliability of the electricity grid.

In June 2021, NRG notified PJM of its intention to retire Indian River 4 in 2022. Based on this notification, PJM conducted a reliability analysis, which indicated that the unit’s removal would lead to grid reliability issues and identified a series of transmission solutions to address those issues.

Based on the estimates for engineering, design, siting, permitting and construction, PJM estimated that the unit would be needed through the completion of necessary transmission upgrades in December 2026. PJM formally requested of NRG to continue to operate the unit during this time frame to provide critical energy, voltage and reactive power support under a Reliability Must-Run (RMR) arrangement. NRG agreed under a rate schedule approved by the Federal Energy Regulatory Commission.

As of Dec. 18, 2024, Delmarva Power completed the Vienna-Nelson line upgrade, the final segment of the necessary transmission upgrades that will allow Indian River 4 to be removed from the system without causing grid reliability issues. PJM has therefore notified NRG of its intent to terminate the RMR arrangement.

The RMR arrangement will terminate officially in February 2025, approximately 22 months ahead of schedule. Terminating the RMR arrangement early will provide consumers with savings estimated by PJM at approximately $93 million, according to the settlement rate filed with FERC and pending Commission approval.

 

NEW Topics