New York Gov. Kathy Hochul on June 17 announced the completion and energization of Smart Path Connect, a 100-mile transmission project.
Developed collaboratively by the New York Power Authority and National Grid, the project unbottles existing and new renewable resources along its path, including low-cost hydropower from the St. Lawrence-Franklin D. Roosevelt Power Project in Massena.
The effort involved construction in two separate transmission corridors, the upgrade of approximately 100 miles of transmission lines, and the construction of four new substations as well as upgrades to 10 existing substations. The project spans Clinton, Franklin, St. Lawrence, Lewis and Oneida counties.
Hochul's office said the project will provide approximately $438 million in annual benefits to New Yorkers, including monthly savings on electric bills for households and businesses.
The modernized energy pathway is the latest project to be completed as part of the largest investment in New York’s electric grid in 50 years.
Now in service in the North Country and Mohawk Valley, Smart Path Connect enables the flow of more renewable energy across New York State, enhances the reliability and resiliency of the state power grid, and reduces costly transmission congestion.
The project also advances Hochul’s commitment to a reliable, affordable and clean energy future for New York by unlocking 1 GW of renewable energy in Upstate New York.
“Smart Path Connect’s completion delivers hundreds of millions of dollars in annual savings and measurable benefits to communities and businesses across New York,” Hochul said. “By modernizing this essential energy infrastructure, we are moving clean power more efficiently and eliminating bottlenecks that have driven up energy costs. The upgraded corridor not only unlocks renewable energy, it also strengthens grid reliability and secures a thriving economic future for all New Yorkers.”
“Through the Smart Path Connect transmission project, under Governor Hochul’s leadership, we are modernizing energy infrastructure to help ensure the lights stay on and that we are lowering energy costs for New Yorkers," New York Power Authority President and CEO Justin Driscoll said. "Congratulations to our team at the Power Authority, National Grid and union laborers that worked through Upstate New York winters, a global pandemic, and several technical challenges to deliver this project on time, resulting in a power grid built to withstand extreme weather events and increasing energy demands.”
The Power Authority built and energized three new substations, made significant modifications to six existing substations, and completed 45 miles of new transmission lines between Clinton and Massena in the North Country.
NYPA’s new digital substations include Haverstock in Massena, Willis Annex in Chateaugay, and Adirondack in Croghan. National Grid completed construction of the project’s southern alignment, a 55-mile segment between the towns of Croghan and Marcy, including constructing a new substation, Austin Road, in the Lewis County town of Glenfield.
The two Smart Path Connect segments are linked by NYPA’s 78-mile Smart Path transmission project — the mid-2023 reconstruction of the Moses to Adirondack transmission lines — forming nearly 200 uninterrupted miles of upgraded 345 kilovolt (kV) transmission between Clinton and Oneida counties -- 345 kV cables have the capacity to efficiently move massive amounts of extra high-voltage power across long distances.
Like Smart Path, Smart Path Connect was primarily built within existing transmission rights-of-way.
In addition to Smart Path and Smart Path Connect, several other large transmission projects have recently gone into service or are awaiting final permits. The Champlain Hudson Power Express transmission project, developed by Transmission Developers Inc., began commercial operation at the beginning of this month. Propel NY Energy, a collaboration between NYPA and New York Transco to strengthen transmission pathways in Westchester, the Bronx and Queens, and Long Island, is advancing its permitting milestones. National Grid’s Upstate Upgrade, a portfolio of more than 70 transmission-related projects to be completed by 2030, is underway in areas across Upstate New York to deliver a smarter, stronger, more reliable energy grid for the future of New York. New York’s recent major transmission investments total hundreds of miles of new and upgraded transmission lines that are bolstering the state’s energy transition.
For more information about the Smart Path Connect project, visit the Power Authority’s Smart Path Connect website. Visit NYPA Transmission for more information about NYPA’s transmission portfolio, interconnection projects and NYPA’s operation and maintenance of one-third of the state’s high-voltage transmission system. For more information about National Grid transmission projects, visit the company’s Upstate Upgrade Project Hub.