New York Transco and the New York Power Authority on Nov. 20 announced the selection of contractors to perform initial Propel NY Energy work, as well as key equipment suppliers following state approval of two construction plans. 

Propel NY Energy is a 90-mile underground and submarine electric transmission project spanning parts of Long Island, Queens, the Bronx, and Westchester County designed to improve the reliability, resiliency, and capacity of the New York State grid.  

On Nov. 19, 2026, the New York State Public Service Commission (PSC) approved the project’s Phase 1 and Phase 2 Environmental Management and Construction Plans (EM&CPs), after several months of public comment and regulatory reviews.  

These approvals come a day after the New York Independent System Operator, the state’s grid operator, released its 2026 Reliability Needs Assessment stating that Propel NY will provide significant benefits to statewide resource adequacy and strengthen reliability between Long Island, New York City and the rest of the state. 

EM&CPs are a required part of the state permitting process to detail how the project will be built in compliance with all applicable laws and the conditions that resulted from the September 17 PSC permit approval. 

Due to the nature and scale of the Propel NY project, multiple EM&CPs will cover different regions and scopes of work. The companies selected through the procurement process for Phase 1 and Phase 2 construction activities bring extensive experience delivering complex infrastructure projects and a strong commitment to employing a highly skilled, union workforce, NY Transco said.

Additional contractors for other phases of work will be announced upon the conclusion of the procurement process.

Throughout an anticipated four-year construction period and across all phases of work, the project will support an estimated 2,000 jobs annually, while boosting the local and regional economy by an estimated $2.4 billion. 

“Propel NY Energy will deliver a more reliable energy future for New York while creating meaningful economic opportunities for communities along the project route. The recent construction plan approvals and the contract awards to our construction partners underscore project maturity and readiness for construction,” said Joris Veldhoven, President, New York Transco. “We’re pairing best-in-class companies with skilled union labor to responsibly build infrastructure that safeguards communities and the environment, strengthens the grid, and supports family-sustaining jobs.” 

“Propel NY Energy is an important infrastructure project that will increase energy capacity and access to clean, reliable power and improve resiliency for the electric system, specifically during high demand and severe weather incidents,” said Justin E. Driscoll, President and CEO, New York Power Authority. “To deliver this major grid modernization project, NYPA along with our development partner NY Transco, are enlisting the expertise and experience of a stable of union laborers and qualified contractors. Our team is working closely with communities along the project route and responsible contractors to ensure the project proceeds in a safe and timely manner to deliver the project’s benefits to New Yorkers.”

EM&CP Phase 1 

EM&CP Phase 1 focuses on vegetation management at the Long Island substations. The plan was initially filed on June 22, 2026, agency and public comments were incorporated, and an updated plan was refiled on October 9, 2026. 

Burns & McDonnell was selected to serve as the prime contractor for the project’s three new Long Island substations that will be built on existing utility-owned property adjacent to existing stations -- Shore Road, Ruland Road, and Barrett. 

Haugland Group and Hitachi Energy will work alongside Burns & McDonnell as key subcontractors. 

Additionally, the project proactively procured critical long-lead equipment from SGB-SMIT Group and Hitachi to support timely execution of key project milestones. 

EM&CP Phase 2 

EM&CP Phase 2 outlines construction activities for specific portions of the project involving horizontal directional drilling (HDD) at the two landfall locations to support future submarine cable installation. The plan was initially filed on July 10, 2026, agency and public comments were incorporated, and an updated plan was refiled on October 16, 2026. The Crossing Group has been selected to execute trenchless crossings (HDD) for the landfall of the submarine crossing from New Rochelle to Glen Head. The Crossing Group is partnered with Hallen Integrated Construction Services (HICS) to complete the work.  

Transmission Cable 

The contractors selected for supplying the terrestrial cable are LS Cable & System and Taihan, both of which have extensive experience delivering large-scale transmission projects in the U.S. and around the globe. 

These companies will be working with local contractors to install and splice the cable. LS Cable & System will also supply and install the submarine cable. 

Pending additional approvals, Propel NY Energy anticipates beginning construction early next year with site work at discrete areas along the route. More active construction is anticipated to begin in mid-2027. 

Construction will be executed in segments and phases, with multiple crews operating at various locations simultaneously to deliver the project in 2030. 

To maintain the ongoing commitment to community engagement, the next quarterly project webinar will be held on Dec. 15 at 6 p.m., providing stakeholders with an opportunity to receive project updates and submit questions directly to the team. 

The webinar will also detail several new public outreach tools, including a redesigned website to track future construction progress with an interactive project map, a new animated construction educational video, a soon to be launched 24/7 staffed inquiry hotline, and an online inquiry form to help community members easily access information and stay connected throughout construction.

 

 