Fervo Energy, a next-generation geothermal energy company, on Nov. 18 announced it has executed a new 105 megawatt Transmission Service Agreement (TSA) with Longroad Energy for its Cape Station development in Utah.
The agreement gives the company long-term, firm delivery rights on the Milford Gen Lead line and builds on the parties’ existing 400 MW arrangement, bringing Cape Station’s total contracted long-term firm transmission capacity to 505 MW. "This new capacity provides a strong foundation for Cape’s continued growth," Fervo said.
The new TSA is expected to begin in 2028, subject to final regulatory approvals.
Fervo Energy is developing the multi-phase Cape Station geothermal development located in Beaver County, Utah, northeast of Milford.
Phase I is on track to begin delivering power to the grid by late 2026, reaching approximately 100 megawatts of operating capacity by early 2027. Phase II is targeted for 2028.