Brattle Group experts, in collaboration with Sargent & Lundy, have completed a study prepared for the Electric Reliability Council of Texas that provides updated Cost of New Entry (CONE) estimates and examines how equipment shortages, construction constraints, and uncertainty about future market conditions affect the revenues needed to support investment in new gas-fired generation.
The study finds that overnight capital costs for gas-fired generation have more than doubled in real terms over the past three years.
Strong demand, combined with supply chains that are slow to expand, has increased costs and extended development timelines. Shortages of turbines, other major equipment, labor, and engineering, procurement, and construction contractors contribute to both higher prices and cost volatility.
The authors’ July 2026 estimates for a 440 MW simple-cycle plant using an H-class frame turbine include:
• Elevated capital costs: Overnight costs approach $1,850/kW with installed costs at $2,350/kW (2026 $) when including capital carrying costs during construction.
• Growing turbine backlogs: Orders at the three largest turbine manufacturers reached 246 GW in Q2 2026, compared to an annual production of approximately 60 GW today and potentially increasing to 80 GW per year by 2030.
• Longer development timelines: New projects initiated today are unlikely to enter service before 2032. Projects that utilize pre-reserved turbines and can begin construction right away and could achieve commercial operations earlier, by late 2030.
• Greater revenue requirements: Estimated CONE is approximately $340/kW-year for a 2030 online date, assuming constant nominal revenues over 20 years. Initial revenue requirements could approach $600/kW-year if investors expect scarcity prices to only last five years before reverting to a long-run equilibrium.
The authors also provide an indicative long-run equilibrium CONE benchmark of approximately $150/kW-year for projects entering service sometime after 2032, once current supply constraints ease.
This benchmark assumes that turbine, equipment, and labor costs return to levels preceding the recent price increases. The study identifies substantial uncertainty around both the timing of that adjustment and the resulting costs, with a potential range of approximately 25% above or below the benchmark.
The study was authored by Brattle Principal Sam Newell, Energy Associate Andrew W. Thompson, Energy Specialist Nathan Felmus, and Energy Analyst Andrew Boettcher, and Sargent & Lundy’s Joshua Junge and Daniel Harrington.