The PJM Board of Managers has authorized changes in scope and cost to some baseline projects in its Regional Transmission Expansion Plan (RTEP), the grid operator said on Nov. 18.

The most significant scope/cost changes were associated with projects assigned to Valley Link VA Inc., a consortium of Transource, Dominion Energy and FirstEnergy, as part of 2024 Window 1, as well as other transmission projects awarded to Exelon and various subsidiaries as part of three separate competitive windows, PJM said.

Valley Link Changes

The Valley Link projects consist of two major 765 kV transmission lines and associated substations. They provide a new extra-high-voltage backbone capable of moving large amounts of power across the PJM west-to-east transmission corridor to address projected load growth and shifting bulk power flow patterns that will lead to future overloads in certain areas that must be addressed to maintain system reliability.

The total cost estimate rose from approximately $3.0 billion (2024 dollars) to $5.1 billion (2026 dollars).

In addition, major Valley Link project components’ in-service dates have shifted from June 1, 2029, to January 2030 through May 2031, depending on the facility.

The primary cost drivers are construction labor/outside services, reflecting significant national infrastructure investment that is driving competition for highly skilled construction resources; right-of-way and land costs, which continue to increase at unprecedented multiples; and material and equipment costs, which increased from the original bid assumptions.

Revised in-service dates reflect the results of post-award project development, including more detailed routing analysis, expanded stakeholder and regulatory engagement and further development of permitting and other required approvals.

Exelon Projects

Much of the work awarded to Exelon and its subsidiaries is related to upgrades that must be in place before the Brandon Shores and Wagner generating units in Maryland can retire. 

If the needs aren’t addressed in a timely manner, it will increase the likelihood of having to continue running those units under a Reliability Must-Run arrangement, which poses a higher reliability risk to the system accompanied by additional costs, PJM said.

Across the projects, costs increased by $783 million for an updated total of $1.69 billion.

Primary drivers included increases in electric utility labor rates for engineering, construction and commissioning services, driven by a combination of workforce shortages, unprecedented infrastructure investment, competition for skilled resources, wage inflation and project complexity, the grid operator said.

Projects Remain Effective Solutions

PJM noted it closely scrutinizes cost increases and reviewed them with the TEAC. "The underlying reliability needs have not changed, the timeline for addressing them is increasingly acute, and in some cases, original project in-service dates have slipped by nearly two years," it said.

PJM staff recommended that the Board move forward with these projects due to the effectiveness of the solutions, the urgent nature of the need and the industrywide cost pressures that would apply to similar solutions.

"Further delays to these projects would likely lead to no change in the solution nature, extend regulatory process timelines and consequently costs, and delay the implementation of acutely needed transmission infrastructure," PJM said.

The RTEP process, which takes place all year long, identifies needs of the grid up to 15 years into the future.

PJM’s RTEP analysis identifies system violations to reliability criteria and standards, determines the potential to improve the market efficiency and operational performance of the system, and incorporates any public policy requirements.

PJM then develops transmission system enhancements to be integrated into a regional solution and reviews them with stakeholders through the TEAC before submitting recommendations to the PJM Board of Managers for consideration at its quarterly meetings.

 

 