The North American Electric Reliability Corporation on Nov. 18 said that its 2026–2027 Winter Reliability Assessment (WRA) finds that resource additions, delayed retirements and better generator performance in cold weather have improved the overall reliability outlook for the upcoming winter. 

However, while all areas are assessed as having adequate resources for normal winter peak load, extreme wide-area winter conditions may result in electricity supply shortfalls. Furthermore, this year’s El Niño weather system, which introduces an additional layer of unpredictability, may also cause disruption, NERC said.

System operators and energy officials are encouraged to become familiar with the recommendations in the 2026–2027 WRA and the joint FERC, NERC and Regional Entities’ Winter 2026 Arctic Cold Period System Performance Review and visit NERC’s new Cold Weather Risk Mitigation web page to help prepare and operate reliably in potentially extreme winter conditions, NERC said.

Although recent reports from NERC and the ERO Enterprise highlight measurable improvements in industry’s cold-weather performance largely due to improved preparation and the implementation of freeze protection measures, NERC President and Chief Executive Officer Jim Robb cautioned, “While the resource outlook has improved, the unpredictable weather of El Niño and rapid load growth present unique challenges this winter. We anticipate operators will need everything in their tool kit—including requests for emergency support—to maintain reliable operations.”

Winter peak demand continues to grow rapidly, primarily due to data center expansion, and electrification resulting in a higher demand forecast for 21 of the 23 NERC assessment areas.

Resource additions are helping improve system adequacy for this winter. However, natural gas remains essential in supporting the electric system during the winter. Consequently, several areas are identified as being at elevated risk of fuel supply availability for natural-gas-fired generation in prolonged cold weather and from localized constraints.

“Regionally constrained natural gas infrastructure limits available fuel for generators during cold snaps, risking outages when generators lack alternate fuels,” said Mark Olson, NERC’s manager of Reliability Assessments. “For example, gas-fired generators in the Pacific Northwest are predominantly single-fuel, exposing them to more fuel risk during peak demand periods.”

Reflecting the criticality of electric-natural gas system planning and operations coordination, this year’s WRA includes an analysis of risks and trends related to the natural gas system for the upcoming winter—which is new to the WRA.

Undertaken annually in coordination with the Regional Entities, NERC’s WRA examines multiple factors that collectively provide deep and unique insights into reliability risk. 

This year’s assessment, summarized in the WRA snapshot, makes a series of recommendations to reduce the risks of energy shortfalls on the bulk power system this winter:

Cold Weather Preparations

Reliability Coordinators (RC), Balancing Authorities (BA), and Transmission Operators (TOP) should review seasonal operating plans and the protocols for communicating and resolving potential supply shortfalls in anticipation of potentially high generator outages and extreme demand levels. Successive overlapping arctic air mass events in January 2026 demonstrated the need for operations planning to consider the potential for extreme conditions to last for 10 days or more and stress the endurance of the BPS, natural gas infrastructure, and operators. 

Operators should review NERC’s ERO Enterprise Extreme Cold Weather - Themes and Best Practices. 

Generator Owners (GO) should complete winter readiness plans and checklists prior to December, deploy weatherization packages well in advance of approaching winter storms, and frequently check and maintain cold weather mitigations while conditions persist.

Load Forecasting

BAs should be cognizant of the potential for short-term load forecasts to underestimate load in extreme cold weather events and be prepared to take early action to implement protocols and procedures for managing potential reserve deficiencies. Proactive issuance of winter advisories and other steps directed at generator availability contributed to improved reliability during cold weather events of the past two winters.

Fuel

RCs and BAs should implement generator fuel surveys to monitor the adequacy of fuel supplies in addition to maintaining contact with pipeline operators and prepare responses to any impactful operational flow orders. 

They should prepare their operating plans to manage potential supply shortfalls and take proactive steps for generator readiness, fuel availability, load curtailment, and sustained operations in extreme conditions. 

GOs/Generator Operators of natural-gas-fired units should maintain awareness of potential extreme cold weather developing over holiday weekends and the implications for fuel planning and procurement that may result given the natural gas purchase close dates that precede long holiday weekends.

Regulation and Policy

State and provincial regulators can assist grid owners and operators in advance of and during extreme cold weather by maintaining awareness of balancing authority, natural gas pipeline, and gas local distribution company operational public announcements and notices, amplifying public appeals for electricity and natural gas conservation, and supporting requested environmental and transportation waivers.